Command Center

Command Center

Overall turnaround status and unit performance

70 hrs
Total Budgeted Hours
25 hrs
Actual Hours to Date
2 / 8
Activities Complete
Overall SPI
1.00On Target0.001.50
Overall CPI
0.64Critical0.001.50
$5,950
Budget
0
IWRs Pending
0
IWRs In Review
0
IWRs Approved
0/1
Hydro Tests
0%
0/2
Tube Inspections
0%
% Complete
25%At Risk0%100%

ALKY

BEHIND
Inspection Tasks
1 / 5
Hours Burn
16 / 50
Budget
$4,250
Est. at Completion
$6,800
Variance
+60.0%
SPI
1.00
Schedule
CPI
0.50
Cost
View Details →

GASCON

AT RISK
Inspection Tasks
1 / 2
Hours Burn
9 / 14
Budget
$1,190
Est. at Completion
$1,530
Variance
+28.6%
SPI
1.00
Schedule
CPI
0.89
Cost
View Details →

MSCC

ON TRACK
Inspection Tasks
0 / 1
Hours Burn
0 / 6
Budget
$510
Est. at Completion
$510
Variance
0.0%
SPI
1.00
Schedule
CPI
1.00
Cost
View Details →

Inspection Progress by Equipment Type

HX0% (0/2)
PUMP0% (0/1)
RX33% (1/3)
COL50% (1/2)

Turnaround Projection

Planned Finish
2026-04-19
Projected Finish
2026-04-19
ON SCHEDULE
Est. at Completion / Variance
$8,500
-$2,550 (42.9%)
D1
D2
D3
D4
D5
D6
D7
D8
D9
D10
D11
D12
D13
D14
Planned Spending
Actual Spending

Active Alerts

No active alerts — all clear